A sales model has one date that matters: the day the sales suite opens. Work back from it.
Your date,
worked back
Nine weeks,
five steps
Start the conversation
Send the drawings you have. We answer within one working day, in your language, with questions and a price.
Order and final drawings
Elevations, floor plans, a roof plan, sections and a colour scheme, ideally in AutoCAD (.dwg). The first week goes to preparing them for the workshop. Missing drawings can be completed for a fee.
The build begins
Four weeks of laser and CNC cutting, hand assembly and airbrush painting, with photographs of the work in progress for your approval.
Crated and shipped
Door to door by FedEx or DHL, about a week, to any continent.
In place
Time to set the model in the sales suite and light it before the doors open. Five renderings of the finished model follow.
These dates hold when the drawings do. Around Chinese New Year (about two and a half weeks), Labour Day (1 to 5 May) and the National Day week (1 to 7 October) the workshop is closed, and the planner allows for it. Less than seven weeks to go? Write anyway. Whether a closer date can be met depends on the size of the model and on what the workshop is building at the time.
How long
it takes
| The model | Time to build | Good to know |
|---|---|---|
| An update to an existing model | About two weeks | A new phase or a replaced building on a base we built earlier. In 2024 a new building for an existing base took eight working days. |
| A single building, or a Slice | About four weeks | The Slice is a single facade, built at scale and framed. |
| A sales model of one development | About four weeks | Usually 1:75 to 1:300. Lighting per apartment is planned in from the start, so mention it at the order. How it works |
| A masterplan or a district | Four to six weeks | Usually 1:500 to 1:1000. A plan built in phases is designed for updates from the first day. How |
| A very large or very detailed model | Longer; the quote states it | Museum pieces at 1:25, models in several sections, many separately lit units. |
Add about a week of courier and a week on site to place the model. Each time holds when the drawings are complete and do not change: what can change, and until when.
Start from the date. We build back from it.